Hanging Rock Hill Repairs Drawing To An End

Hope to reopen at end of month

SR 7, Hanging Rock Hill in Madison crews are excavating the existing roadway near the soil nail wall that was recently completed on the hillside.

Next steps include sub-grade treatment, concrete curb installation and paving.

The hill is expected to reopen by the end of September. The Road has been closed since May.

More from Local News

Events

Local News

Gov. Beshear Demands Sen. McConnell Provide 'Proof of Capacity to Serve'

McConnell issued a statement this week as he continues to recover from a fall in June

South Ripley Community School Corporation Superintendent Named 2027 Indiana Superintendent of the Year

Superintendent whose leadership exemplifies excellence in public education

Save the Date: Swiss Wine Festival is Almost Here

Celebrate Vevay's Swiss heritage August 27-30

Local Sports

Pacer Coaches, Parents, Student-Athletes Invited to Attend Screening of "Not Good Enough"

The award-winning documentary explores the damaging effects of excessive perfectionism and pressure on student-athletes