Update On Milton-Madison Bridge Approach

Beaty also stated that the pedestrian walkway on the bridge will reopen soon as well.

(Madison, Ind.) – During their second meeting of the month on Monday, the Madison Board of Public works provided updates on the Milton-Madison Bridge approach project.

Kyle Beaty of Beaty Construction joined the board to speak about the approach stating that there has been a delay in the project, so the completion date will be later than originally announced. A majority of the work which includes drainage, concrete pouring, and infrastructure will be completed by mid-December.

Crews will then return again in April to complete the surface pavement and permanent pavement markings, which are both temperature-sensitive. The temporary traffic signal that is in place will be removed and a four-way traffic signal will be put into operation.

Beaty also stated that the pedestrian walkway on the bridge will reopen soon as well.

More from Local News

Events

Local News

Gov. Braun Announces $207 Million Federal Grant to Launch GROW: Cultivating Rural Health 

The five-year initiative is designed to enhance healthcare access and data, quality, and outcomes through system innovation and collaboration.

Local Sports

Local Sports for December 30, 2025

Jefferson County Invitational Tournament along with Several Other Area Tournaments

Local Sports for Dec 29, 2025

Jefferson County Invitational Tournament along with several other area tournaments

LOCAL SPORTS FOR NOVEMBER 18, 2025

Any missing scores or to report a score email news@953wiki.com