Culvert Replacement
Indiana Department of Transportation officials met with contractor representatives this morning (JAN 22) at Seymour District offices to review plans for removing and replacing a small structure under State Road 250 in Cotton Township.
OLCO Inc of Batesville is the state’s contractor for this $220,263 project. Its crews are scheduled to begin excavation work in April—requiring the closure of S.R. 250 at the worksite located five miles east of S.R. 129 in northwest Switzerland County.
A state highway detour will utilize S.R. 56 and S.R. 129.
During the closure, OLCO crews will remove the existing S.R. 250 structure and replace it with a precast 4-sided reinforced concrete box culvert. The new installation will have a 6-foot span and 4-foot rise. It will measure 48 feet in length.
S.R. 250 has a traffic count of 1,050 vehicles per day.

Crane Operator Sustains Fatal Injuries in Brent Spence Bridge Corridor Accident
Indiana State Police Partners with DEA for Drug Take Back Day
Milton Fire & Rescue Awarded $390,450 FEMA SAFER Grant to Support Volunteer Recruitment and Retention