S.R. 256 to reopen east of Austin for winter shutdown

Will close again in the Spring

 State Road 256 east of Austin is scheduled to reopen for the winter months on Monday (Dec. 16), weather permitting. Indiana Department of Transportation contractor Milestone Contractors resumed work on the nearly $18 million, multi-phase reconstruction project this past April. 

The project includes rebuilding and widening S.R. 256 between U.S. 31 and S.R. 203 in Scott County, in addition to replacing the bridge over Hutto Creek, intersection realignment at Coffee Pot Road and adding a center left turn lane at S.R. 203. 

  

Crews will complete temporary striping and guardrail installation through the remainder of this week and the weekend before opening the roadway.

The completion date for the entire project is October 2021, but work is currently progressing ahead of schedule. S.R. 256 will close again in early spring 2020 for the project to continue.

More from Local News

Events

Local News

Bartholomew County Man Arrested for Child Molesting

Months long investigation led to the arrest

Indiana State Police Investigating Death of Inmate

The investigation remains ongoing

Local Sports

ORVC Weekly Report Summary (April 15 – 20) 2024

Congratulations to all the area athletes that received honors