Small Structure Replacement to begin April 3 on S.R. 56 in downtown Madison

CLOSED FOR APPROX 60 DAYS BEGINNING APRIL 3RD

                                SR 56

JEFFERSON COUNTY, Ind.— Indiana Department of Transportation contractor Dave O’Mara Inc. plans to begin work next week on State Road 56 between Ferry Street and First Street in downtown Madison.

Beginning on or after Monday, April 3, S.R. 56 will be reduced to one lane in each direction controlled by temporary traffic signals to allow crews to complete a small structure replacement. Access to S.R. 56 from Ferry Street and First Street is expected to be closed for approximately 60 days, weather permitting.

The contract was awarded to Dave O'Mara Inc. in August 2022 for $1.3 million and is expected to be complete by late September. INDOT reminds drivers to slow down, avoid distractions, and consider worker safety when traveling through active construction zones. All work is weather-dependent and schedules are subject to change.

More from Local News

Events

Local News

Madison City Council Approves Two Bond Issuances to Support 2027 Parks Investment Strategy

Continued investment in local parks and recreational facilities

Madison Man Sentenced to 18 Years for Dealing Methamphetamine

This sentence demonstrates that accountability must take precedence

2026 General Election Results

Republicans sweep Jefferson County and also in Trimble County

Local Sports

SEI Soccer Players Earn Academic All-State Honors

The list of local recipients is long!

High School Football Sectional Semifinal Recap

Six local teams remain alive in the IHSAA Football State Tournament

Jennings County Football Coach Submits Resignation

Jason Burton led the program for three years.